Page 11 - Annual Report 2008
P. 11
2008
AnnuAl RepoRt Laporan Tahunan
COrpOraTE iNFOrmaTiON


DEVElOpmENT


plaNS


the major development of the Board under the 9th Malaysia plan included implementation of the following
projects:

(i) expansion of salim treatment plant
• A new raw water intake
• A 75 MLD treatment plant

(ii) renewal of pipelines in Various parts of sibu town (on-going)



DEVElOpmENT prOGrESS

2008 is the third year of 9th Malaysia plan. the Board spent rM33.4 million on development during the year.
out of this amount, rM30.0 million (90%) was spent on expansion of salim treatment plant phase ii, rM2.1
million (6%) was spent on renewal of pipelines, rM0.9 million (3%) was spent on Upgrading of stabau
Booster station, and the balance of rM0.4 million (1%) accounted for the normal extension of pipeline.

the Board saw the completion of three (3) mains renewal projects which commenced in the previous years.
another four (4) contracts awarded during the previous years, namely, salim treatment plant phase ii, stage
1 and stage 2, the Mains renewal project at Jln tun abg hj openg and Upgrading of stabau Booster station
were still in progress at the end of the year.


the Board awarded four (4) development projects comprising three (3) nrW projects and Upgrading of
salim-sibintek-durin Water pumping system during the year. two of the nrW projects had been completed.

a summary of the development projects for the year is shown below:


(i) Contract No. SWb/CT/07/2006
The Delivery and laying of D.i./hDpE mains, Valves & Fittings Cum ancillary Works along
Jalan Tun abang haji Openg, Sibu (mains renewal).

Contract sum: rM2,180,804.00
revised Contract sum: rM457,946.58
Contract period: 18.09.2006 – 17.09.2008
supplementary Contract period: 21.10.2008 – 06.03.2009
Contractor: Mainline enterprise sdn.
Bhd.
physical Work done up to 31.12.2008: 83.59%
scheduled progress up to 31.12.2008: 37%
Remarks: • Project was partially
completed on
29.02.2008 due to stopage of drainage work by JKr
• Defects liability period for the completed portion will
expire on 28.02.2009
• A supplementary agreement was made with contractor to
continue the remaining portion when JKr resumed the
drainage work in october 2008.


8