                                Progress                                 dEVELoPMEnT







               PLans
               The major development of the Board under the last of 11  Malaysia Plan included implementation
                                                                       th
               of the following projects:

               1.  Program Mengurangkan Kadar Air Tak Terhasil Negeri Sarawak (Fasa 2)
               2.   Membaikpulih Sistem Agihan Negeri Sarawak (Fasa 2)
               3.   Tanjung Manis Water Supply Phase 1



               dEVELoPMEnT ProgrEss
               The Board had allocated RM11.46 million for development projects in 2017, which marked the
               one (1) year @  second of the 11  Malaysia Plan. Total amount spent was RM7,456,088 which was
                                               th
               made up of NRW (Fasa II) RM5,570,700 or 75%. Membaikpulih Sistem Agihan Negeri Sarawak
               RM1,199,147 or 9% and other development RM686,241 or 16%. For water supply project for
               Pulau Bruit and Paloh allocated RM10 Million.

               1.  Contract No. SWB/CT/23/2013  Tanjung Manis  Water
                   Supply Phase 1 Package 1 – Proposed Raw  Water
                   Intake Using River Bank Filtration System (RBF)

                   Contract Sum : RM73,987,000.00
                   Date of Commencement : 11.11.2013
                   Date of Practical Completion : 16.03.2016
                   Contractor : KCK Konsortium Sdn. Bhd.
                   Consultant : G&P Professional (Sarawak) Sdn. Bhd.
                   Physical Work Done up to 31.12.2017 : 71.49%
                   Scheduled progress up to 31.12.2017 : 100%


                   Remarks :
                   Due to non-compliance to the technical specification, the constructed River Bank Filtration
                   (RBF) system was unable to produce the minimum required yield of 125MLD of raw water in
                   the tests conducted in Year 2016, which was recorded a total of 51.541MLD of raw water. Apart
                   from yield issue, during the  Testing and Commissioning (T&C) of  Water  Treatment Plant
                   (Package 6 project) in July 2016, issue in raw water quality from RBF causing the water to be
                   untreatable.


                   Due to the defaults by Contractor, the employment of the Contractor had been determined by
                   SWB on 8 November 2017. Currently, dispute had aroused between SWB and KCK, and it is
                   under adjudication proceeding and also the stage of dispute resolution. There was also payment
                   issue, which the project was under Construction Industry Payment and Adjudication Act 2012
                   (CIPAA) adjudication.